GIS Campus Reimagined
Building on Excellence
We are delighted to share with you the exciting new development we have planned for our main campus.
These new developments will result in a world-class Sports Complex, an outdoor Sports Field and a basement car park in Phase 1, followed by Phase 2 where an Alfresco Dining Space, Multi-Purpose Play Area, FIFA Youth Field Size will be unveiled.
Our Virtual Tour
GIS Campus Reimagined
Why Reimagined?
While our priority in undertaking any new development/facilities is to enhance the student learning environment, we also want to ensure that they benefit our wider community. With this in mind, we want to highlight the following key considerations for this project.
01
It’s not about the numbers!
We are re-imagining to enhance the facilities of the school, NOT to increase our student capacity.
02
Student Learning Environment
Our priority is always to create enhanced learning experiences for our students, with top-of-the-range facilities for a world-class education.
03
Supporting our Community
The addition of a new world-class sports centre (and the future performing arts centre) will be a boon to the wider community who may be looking for a venue/location for sporting, performance and/or community gatherings outside of our regular school hours.
We have reached out to representatives from our neighbour community to update them on the project and let them know of the potential future benefits for our wider community.
04
Smoother Traffic Flow
We realise that traffic is a key challenge for the school and our neighbouring areas. Therefore, we have put in place several strategies to try to help minimise traffic during pick-up and drop-off times, as follows:
- Staggered school hours for different phases of the school to help smooth the traffic flow during drop-off and pick-up times.
- Encouraging students who live within walking distance to walk to school. Currently, about 35% of GIS students walk to school.
- Construction of a new drive-through ramp to help streamline traffic flow between Jalan Kiara 3 & Jalan Kiara 5.
- Introducing a free shuttle bus service located near the school in addition to the normal bus service, thereby reducing the number of cars during peak times.
- Prioritising the build sequence to ensure the new basement car parking facility will be available on site while the sports centre fit-out commences.
We are regularly consulting and reviewing our traffic flow solutions with DBKL.
GIS Campus Reimagined
A glimpse of
GIS Campus Reimagined
Check out this fly-thru video to get a sense of what our new and improved facilities will look like.
GIS Campus Reimagined
Our Timeline
Our proposed timeline of the GIS Campus Reimagined development.
Interim Phase (June 2022 - September 2022)
Completion of drive thru ramp to allow dropoff and pickup on campus between Jalan Kiara 3 & Jalan Kiara 5.
Phase 1a (June 2022 - October 2023)
Completion of basement carpark, outdoor sports field and new entrance on Jalan Kiara 3.
Phase 1b (November 2023 - August 2024)
- Fitting out the new sports centre, to be completed around September 2024 which will comprise:
- An Olympic-size swimming pool
- Two indoor basketball courts
- Two tennis courts
- Gym/fitness suite
GIS Campus Reimagined
Phased Approach
Our world-class sports centre will be completed in phases, to ensure that there is minimal disruption to the school environment, student learning and wider community.
Phase 1a — Basement Car Park/Outdoor Sports field
Completed on 28 October 2024
Phase 1A of our campus reimagined project unveiled the following new facilities:
- A new basement car park with drive-thru pick-up and drop-off facilities
- A new astro turf sports field
- A new Gate A walk-in main entrance on Jalan Kiara 3
- Drive-thru access for drop-off and pick-up entering via Gate B on Jalan Kiara 3 and exiting via a ramp to Gate D on Jalan Kiara 5
Phase 1a — Basement Car Park/Outdoor Sports field
Completed on 28 October 2024
Phase 1A of our campus reimagined project unveiled the following new facilities:
- A new basement car park with drive-thru pick-up and drop-off facilities
- A new astro turf sports field
- A new Gate A walk-in main entrance on Jalan Kiara 3
- Drive-thru access for drop-off and pick-up entering via Gate B on Jalan Kiara 3 and exiting via a ramp to Gate D on Jalan Kiara 5
Completed
The new Sports Centre will be a welcome addition to the school’s facilities for GIS and the wider Mont Kiara community. It offers the following facilities:
- An Olympic-size swimming pool
- Two indoor basketball courts
- Two outdoor tennis courts
- Gym/fitness suite
It will also provide a new entrance via Jalan Kiara 5, as well as the Physical Education office and Admissions office.
Phase 2 - Alfresco Dining, Multi-Purpose Play Area, FIFA Youth Field Size
Expected Completion: End of Term 1, 2025/26
Phase 2 will unveil an all-new alfresco dining space, a multi-purpose play area, and the expansion of the sports field into a full-size football pitch — enhancing opportunities for competitive play and community events.